holidays and build dates
#3028262
03/28/22 09:00 AM
03/28/22 09:00 AM
|
Joined: Jan 2003
Posts: 5,120 Chicago Blackhawks
hemicar1971
OP
master
|
OP
master
Joined: Jan 2003
Posts: 5,120
Chicago Blackhawks
|
Did Chrysler use a Holiday Date on the Fender Tag or BCS. An example holidays during the 1971 build. Good Friday or Easter Monday did the plant work on those days in 1971 April 9th, April 12th and did Chrysler put these dates on the fender tags even if there was no production. First did the UAW have these dates in their contract as holidays or maybe just one or those days.
1971 HEMI E BODY REGISTRY
|
|
|
Re: holidays and build dates
[Re: 69CoronetRT]
#3029150
03/31/22 11:19 AM
03/31/22 11:19 AM
|
Joined: Jan 2003
Posts: 3,704 MICHIGAN
DynoDave
master
|
master
Joined: Jan 2003
Posts: 3,704
MICHIGAN
|
This is a great question; something I've been curious about for years. My Charger has a July 4 build date, but I had always assumed that the plant did not work that day (July 4 being a calculated "scheduled build date", not the date it was actually built). But who knows. IF they did work July 4, they got paid double or triple time for it, so it was costly production for Chrysler. But if you are backed up on orders, then maybe it's worth it. Still, kinda cool have a July 4 birthday for my Charger!
Last edited by DynoDave; 03/31/22 11:20 AM.
|
|
|
Re: holidays and build dates
[Re: DynoDave]
#3029178
03/31/22 12:21 PM
03/31/22 12:21 PM
|
Joined: Jun 2004
Posts: 935 Elizabethtown, KY
6T9Hemi
super stock
|
super stock
Joined: Jun 2004
Posts: 935
Elizabethtown, KY
|
I had a set of "H" wheels that were dated July 4th 1968.
1969 340 4 Speed Swinger R4, black vinyl, white butt stripe, 3:91
|
|
|
Re: holidays and build dates
[Re: 6T9Hemi]
#3029233
03/31/22 02:38 PM
03/31/22 02:38 PM
|
Joined: Jan 2003
Posts: 5,120 Chicago Blackhawks
hemicar1971
OP
master
|
OP
master
Joined: Jan 2003
Posts: 5,120
Chicago Blackhawks
|
tI was one of the question or thoughts being tossed around while working on a friends car I found him. Since Easter is just around the corner we looked at April and then wondered about the Holiday in April. Good Friday would of been April 9th in 1971. So did a ton of searches and lots of Challenger built on April 8th 1971, have not come across a Barracuda yet. No VINs with a SPD of April 9, 10, 11, but found one on April 12th but might be a typo on the information. Found another VIN Hamtr. 355515 but could not find a SPD. This VIN likely would have been at this time. I know April was a weird time at Chrysler with things being used up like 1970 Shaker Hoods on 1971 Plymouth E Bodies, and other line work modifications. End of May there was more and all this has an effect on April. The build still is in batches of Dodges and Plymouths but I am not sure how big the batches were. I know from my own Challenger the batches were a lot smaller at the end of May and start of June.
So did the plant run one or two shifts, knowing this and how many were built on a shift then the mathematics can be done. Not all plants would of run overtime on a Holiday and maybe none of them did do to the UAW Contract.
Last edited by hemicar1971; 03/31/22 05:16 PM.
1971 HEMI E BODY REGISTRY
|
|
|
Re: holidays and build dates
[Re: hemicar1971]
#3035399
04/20/22 04:51 PM
04/20/22 04:51 PM
|
Joined: Jan 2003
Posts: 5,120 Chicago Blackhawks
hemicar1971
OP
master
|
OP
master
Joined: Jan 2003
Posts: 5,120
Chicago Blackhawks
|
So April 9th 1971 is Friday and April 11 1971 is Sunday. I was given information on a couple of cars and they seem to be built on April 9th 1971 on G/Friday or the SPD says that. No VINs on April 10th or April 11th but some VINS or SPDs on April 12th. So if you have an E Body built on 408 409 410 411 or 412 413 1971 could you please list it hear of send me a PM.
Thanks
1971 HEMI E BODY REGISTRY
|
|
|
Re: holidays and build dates
[Re: topside]
#3035508
04/21/22 12:33 AM
04/21/22 12:33 AM
|
Joined: Jan 2003
Posts: 5,120 Chicago Blackhawks
hemicar1971
OP
master
|
OP
master
Joined: Jan 2003
Posts: 5,120
Chicago Blackhawks
|
The Idea of collecting this information is to see how many Vehicles were Sched. to be built on these dates and go from there. Gathering Vins and FT dates around this time will further a study on this. I am fully aware of SPD dates. I have a Challenger that has a May SPD date but a June Door sticker. I also know that Dodges at the end of May were running well after the Plymouth when being built,
1971 HEMI E BODY REGISTRY
|
|
|
|
|