Previous Thread
Next Thread
Print Thread
Page 4 of 4 1 2 3 4
Re: OT. Electrician question [Re: Hemi_Joel] #2854828
12/03/20 03:16 PM
12/03/20 03:16 PM
Joined: Jan 2003
Posts: 27,465
So Cal
autoxcuda Offline
Too Many Posts
autoxcuda  Offline
Too Many Posts

Joined: Jan 2003
Posts: 27,465
So Cal
Originally Posted by Hemi_Joel
All I need to run is a small office. Maybe I need to find a 3 phase coffee pot. laugh2


But you do want to make sure the 3 phase is available in future for your speculative development plans.

For what you are thinking, you just need to make sure there are 3 high voltage wires above the transformers. On a pole line near or on your property line. That way you can feed primary voltage underground to a big 3 phase pad mounted transformer and possibly other equipment that would in turn feed a large shopping center.

Re: OT. Electrician question [Re: autoxcuda] #2854831
12/03/20 03:23 PM
12/03/20 03:23 PM
Joined: Jan 2003
Posts: 7,477
Minnesota
Hemi_Joel Offline OP
master
Hemi_Joel  Offline OP
master

Joined: Jan 2003
Posts: 7,477
Minnesota
My building next door has 3 phase for the body shop. I think they both hook up to the same place.


[img]http://i.imgur.com/boeexFms.jpg[/img]
31 Plymouth Coupe, 392 Hemi, T56 magnum
RS23J71
RS27J77
RP23J71
RO23J71
WM21J8A
I don't regret the things I've done. I only regret the things I didn't do.
"Wise men talk because they have something to say; fools because they have to say something. ~ Plato"
Re: OT. Electrician question [Re: Hemi_Joel] #2854841
12/03/20 03:46 PM
12/03/20 03:46 PM
Joined: Jan 2003
Posts: 27,465
So Cal
autoxcuda Offline
Too Many Posts
autoxcuda  Offline
Too Many Posts

Joined: Jan 2003
Posts: 27,465
So Cal
Originally Posted by Hemi_Joel
My building next door has 3 phase for the body shop. I think they both hook up to the same place.


Perfect up

You’re good.

I was just pointing out that if transformers (even entire poles) sit idle, the electric company can remove those as idle facilities.

One example of that around here is when citrus farmers stop service on electric wind machines. The electric company is obligated to take down transformers and poles if they only serve that that one service. After a period of time. Sometimes to put those poles and transformers back up at a later date could have six figure construction cost from electric company. Customers can pay “stand by” fees to keep that from happening if they chose.

Last edited by autoxcuda; 12/03/20 03:47 PM.
Re: OT. Electrician question [Re: Hemi_Joel] #2854878
12/03/20 05:26 PM
12/03/20 05:26 PM
Joined: Feb 2014
Posts: 1,696
central il.
S
second 70 Offline
top fuel
second 70  Offline
top fuel
S

Joined: Feb 2014
Posts: 1,696
central il.
Originally Posted by Hemi_Joel
My building next door has 3 phase for the body shop. I think they both hook up to the same place.


Joel just a thought, you can leave all the 3 phase wiring in place without hooking it back up or paying for it and it will be there if you ever change your mind. Just hook up a single line and meter for your use. After working as a lineman for 40 years I will tell you this happens quite often on commercial buildings.

Mike

Re: OT. Electrician question [Re: autoxcuda] #2854984
12/03/20 10:05 PM
12/03/20 10:05 PM
Joined: Dec 2003
Posts: 22,696
Bitopia
J
jcc Offline
If you can't dazzle em with diamonds..
jcc  Offline
If you can't dazzle em with diamonds..
J

Joined: Dec 2003
Posts: 22,696
Bitopia
Originally Posted by autoxcuda
Originally Posted by second 70
Originally Posted by jcc
Beating a dead horse here it seems, not sure I understand why 3 phase costs more from the utility, usually the main power monthly costs are per kw used, 3 phase has no other real downside, if OP ever finds a use for it, like with a "real" compressor, lathe, mill, etc it will be a real plus if functional, all other normal "single phase" equipment can usually run off of a 3 phase system, and if hell bent on downsizing the existing wiring, ditch the single phase distribution. My leaning towards the 3 phase here is assuming its a 120/208V 3 phase, if a higher voltage system, never mind. grin


It's the cost to the utility. Three phase has to have either 2 or 3 transformers to supply power single phase only 1. So we have to run 3 high voltage power lines,install 3 transformers instead of one. So not only is a 3 phase service higher but the cost of a single phase is higher based on what amp service it is also. So 100amp is less than 200 etc. Each time the amps goes up we have to install bigger wire,transformer,and generate more power.


Exactly iagree

Exactly what? The OP& his utility already has 3 phase in place, there are no additional costs to anybody, he just has to decide which service serves his needs best in the future. my understanding from the utility perspective, they prefer three phase, as that is what comes out of the power plant, and with 3 phase loads, they don't have to deal with balancing the loads as much, just collect the money.


Reality check, that half the population is smarter then 50% of the people and it's a constantly contested fact.
Re: OT. Electrician question [Re: autoxcuda] #2856792
12/07/20 09:01 PM
12/07/20 09:01 PM
Joined: Jan 2003
Posts: 3,623
Millinocket, Maine
J
JonC Offline
master
JonC  Offline
master
J

Joined: Jan 2003
Posts: 3,623
Millinocket, Maine
Originally Posted by autoxcuda
Originally Posted by second 70
Originally Posted by jcc
Beating a dead horse here it seems, not sure I understand why 3 phase costs more from the utility, usually the main power monthly costs are per kw used, 3 phase has no other real downside, if OP ever finds a use for it, like with a "real" compressor, lathe, mill, etc it will be a real plus if functional, all other normal "single phase" equipment can usually run off of a 3 phase system, and if hell bent on downsizing the existing wiring, ditch the single phase distribution. My leaning towards the 3 phase here is assuming its a 120/208V 3 phase, if a higher voltage system, never mind. grin


It's the cost to the utility. Three phase has to have either 2 or 3 transformers to supply power single phase only 1. So we have to run 3 high voltage power lines,install 3 transformers instead of one. So not only is a 3 phase service higher but the cost of a single phase is higher based on what amp service it is also. So 100amp is less than 200 etc. Each time the amps goes up we have to install bigger wire,transformer,and generate more power.


Exactly iagree


11B40
Re: OT. Electrician question [Re: Hemi_Joel] #2857066
12/08/20 01:43 PM
12/08/20 01:43 PM
Joined: Jan 2003
Posts: 8,480
Candler,NC / Myrtle Beach, SC
J
JDMopar Offline
master
JDMopar  Offline
master
J

Joined: Jan 2003
Posts: 8,480
Candler,NC / Myrtle Beach, SC
Joel....look at the power pole closest to this building, and see if it has transformers on it. If it has 2 transformers, there is a strong possibility that the power company can give you 200 amp single phase service by just running a new service line to the building. If it has high voltage lines and no transformers, the power company probably took them down and just left the pole and lines to hold the right of way. They can easily hang a new pot and run a service. If they can't. second 70 and I can! up You can get your electrician to install a 200 amp meter base and 200 amp breaker panel inside if the inside single phase panel doesn't already exist. If you have a Fluke meter, you can tie the ends of the circuits together in the breaker panel, and go to each fixture and ring them out. You can set the Fluke meter to audible tone ohm setting, and not have to look at the meter to know if they ring out. I see your point of not wanting to spend a lot of money for 3 phase service you will never use in an office/storage space. Let the next owner do that after the aforementioned bulldozer is done....lol.

Re: OT. Electrician question [Re: JDMopar] #2870828
01/08/21 02:36 AM
01/08/21 02:36 AM
Joined: Jan 2003
Posts: 7,477
Minnesota
Hemi_Joel Offline OP
master
Hemi_Joel  Offline OP
master

Joined: Jan 2003
Posts: 7,477
Minnesota
I have an update for you. I met over there with a licenced electrician to formulate a game plan. He talked to the electric coooperative. They didn't want anything, just let them know when we are ready. The electrician wanted to rip out all the old panels and meter sockets and conduit and cables, and start from scratch. I asked him to back off on that idea, we will replace what is shot, and reuse what is sensible and safe and economical to reuse.
So he is replacing the meter socket with a new one, and installing an adjacent master cutoff switch on the outside of the building. The meter socket will have two sets of output lugs, one for the main building, and one for the ex-car wash/garage. We will abandon the main cutoff switch and both panels that are in the basement. The new meter socket and main cutoff switch will have a new conduit going up into the attic and over and down to the existing service panel in the upstairs back of the building. There is two panels there, one feeds off of the other. Any circuits that were run off of the panels in the basement are either being abandoned, or they are going to be run up to the panel upstairs. They are planning to start on that next week sometime.
The electric co-op says we are going to stay with the three-phase service, but they no longer have a larger meter charge than single phase, so I have no issue with that.
I ran an extension cord over there a couple weeks ago from my adjacent building, about 350 ft of cord, and we got a furnace running in there and some temporary lights. My handyman guy ripped out the coolers, and removed all of the gas station control equipment and panels from inside the building, removed the conduit and wires feeding them, as well as the wiring that was feeding the walk-in cooler and the walk-in freezer.
Today I went over there with a helper to identify all the circuits. We ran a generator outside, and took an extension cord and cut off the female end, and plugged the male end into the generator. We ran it in through a hole in the wall where conduit had been removed. We took the neutral from the generator cord and hooked it into the neutral bar of the panel upstairs. Then with the breakers all turned off, we took the hot wire and touched the circuit breaker screw on each circuit one at a time. We simultaneously used one of those little current checking sticks and ran around to each outlet and fixture and stuff. And turned on light switches. Most of the lights worked when we powered them up through the breaker. We were able to map out the circuit breakers and label everything and create a chart. Everything that is no longer going to be used was removed from the breaker. So that effort is going to save the electrician a lot of time and save me some bucks.

The electrician looked over our work late this afternoon and gave it his blessing. He is going to run a circuit down into the basement for some lights and an outlet. The furnace circuit is already in the panel upstairs, and so is the sump pump.

Once we started haggling over the scope of work, I agreed to pay him on a time & material basis rather than a lump sum bid. As long as they don't goof around, I think that will work out best in this circumstance. I'll let you know how it comes out. Thanks for all of your help and suggestions!

PXL_20210107_165933132.jpgPXL_20210107_161323602.jpg

[img]http://i.imgur.com/boeexFms.jpg[/img]
31 Plymouth Coupe, 392 Hemi, T56 magnum
RS23J71
RS27J77
RP23J71
RO23J71
WM21J8A
I don't regret the things I've done. I only regret the things I didn't do.
"Wise men talk because they have something to say; fools because they have to say something. ~ Plato"
Re: OT. Electrician question [Re: Hemi_Joel] #2871046
01/08/21 12:40 PM
01/08/21 12:40 PM
Joined: Jan 2003
Posts: 4,142
Canada -- Posts: 4034 -Registe...
5
5thAve Offline
Doesn't care what this says anyway
5thAve  Offline
Doesn't care what this says anyway
5

Joined: Jan 2003
Posts: 4,142
Canada -- Posts: 4034 -Registe...
Sounds like you're getting somewhere with it now.
It doesn't look too bad for an abandoned building, from those 2 pics anyway.

Re: OT. Electrician question [Re: Hemi_Joel] #2871092
01/08/21 01:26 PM
01/08/21 01:26 PM
Joined: Feb 2014
Posts: 1,696
central il.
S
second 70 Offline
top fuel
second 70  Offline
top fuel
S

Joined: Feb 2014
Posts: 1,696
central il.
Maybe you can pay him with one of your gift cards. Lol

Re: OT. Electrician question [Re: second 70] #2871117
01/08/21 01:50 PM
01/08/21 01:50 PM
Joined: Jan 2003
Posts: 7,477
Minnesota
Hemi_Joel Offline OP
master
Hemi_Joel  Offline OP
master

Joined: Jan 2003
Posts: 7,477
Minnesota
Originally Posted by second 70
Maybe you can pay him with one of your gift cards. Lol


Santa4. laugh2

Now you're thinking!

It's interesting on the monthly meter charge. last time I had looked at this several years back, it was $7 a month for single phase commercial, and $49 a month for three phase if I remember right. Now it's $20 a month for either one.


[img]http://i.imgur.com/boeexFms.jpg[/img]
31 Plymouth Coupe, 392 Hemi, T56 magnum
RS23J71
RS27J77
RP23J71
RO23J71
WM21J8A
I don't regret the things I've done. I only regret the things I didn't do.
"Wise men talk because they have something to say; fools because they have to say something. ~ Plato"
Re: OT. Electrician question [Re: Hemi_Joel] #2871140
01/08/21 02:41 PM
01/08/21 02:41 PM
Joined: Jan 2003
Posts: 27,465
So Cal
autoxcuda Offline
Too Many Posts
autoxcuda  Offline
Too Many Posts

Joined: Jan 2003
Posts: 27,465
So Cal
Originally Posted by Hemi_Joel
Originally Posted by second 70
Maybe you can pay him with one of your gift cards. Lol


Santa4. laugh2

Now you're thinking!

It's interesting on the monthly meter charge. last time I had looked at this several years back, it was $7 a month for single phase commercial, and $49 a month for three phase if I remember right. Now it's $20 a month for either one.


Interesting... how different areas to different things.

Is their kWh rate the same for 3ph vs 1ph ?

This is a business rate either way.

Last edited by autoxcuda; 01/08/21 02:43 PM.
Page 4 of 4 1 2 3 4






Powered by UBB.threads™ PHP Forum Software 7.7.1